Masonry works are at 18th floor of Tower B. 

July 16 to August 15, 2010  

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez Concrete hollow block walls and plastering works are at 18th floors of Tower B.


Masonry works are at 18th floor of Tower B.

*NOTE: There is no designated 4th floor.

June to July 2010  

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez Concrete hollow block walls and plastering works are at 18th floors of Tower B.

Pending minor concreting works is the tower crane block-out at ground and 3rd floors respectively.

May to June 2010  

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez Solemare Parksuite Sales Group with ALHI AVP for Sales&Marketing Ms. Beth Sison

Topping off ceremony of Tower B signals start of finishing works

April to May 2010  

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez Solemare Parksuite Sales Group with ALHI AVP for Sales&Marketing Ms. Beth Sison

Concrete hollow block walls and plastering works are at 8th floor.

March to April 2010  

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez Solemare Parksuite Sales Group with ALHI AVP for Sales&Marketing Ms. Beth Sison

Tower B columns and floor slab reached 16th level. Construction of exterior precast wall still ongoing.

February 16 to March 15, 2010 

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez Solemare Parksuite Sales Group with ALHI AVP for Sales&Marketing Ms. Beth Sison

Concreting status to date is already at 10th Floor of Tower B. Exterior precast wall installation is still currently ongoing.

January 16 to February 15, 2010 

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez

Work accomplishment is generally on-schedule with an overall actual physical accomplishment of 33.20 % as against a target of 32.09 % as of 14 January 2010.
Fair weather continues to grace the month which maximizes a good working pace for construction operations, especially for work shifts and material deliveries.

December 16 to January 15, 2010 

ALHI AVP for Sales&Marketing Beth Sison, Host Giselle Sanchez

Concreting status to date is already at 3rd floor of Tower B. Fair weather continues to grace the month which maximized a good working pace for construction operations, especially for work shifting and material deliveries.