Tower A fifth floor mockup unit substantially completed.
July to August 2010
Tower A fifth floor mockup unit substantially completed.
*NOTE: There are no 4th, 13th and 14th floor designations
June to July 2010
Pending minor concreting works is the tower crane block-out at ground and 3rd floors respectively.
May to June 2010
Topping off ceremony of Tower A signals start of finishing works
April to May 2010
Concreting status for floors and columns has reached roof deck of Tower B
March to April 2010
Tower A columns and floor slab already reached the roofdeck. Construction of exterior precast wall still ongoing.
February 16 to March 15, 2010
Concreting status to date is already at the 18th Floor of Tower A. Major concrete pouring is now focused at tower levels. Exterior precast wall installation is still currently ongoing.
January 16 to February 15, 2010
Work accomplishment is generally on-schedule with an overall actual physical accomplishment of 33.20 % as against a target of 32.09 % as of 14 January 2010.
Fair weather continues to grace the month which maximizes a good working pace for construction operations, especially for work shifts and material deliveries.
December 16 to January 15, 2010
Concreting status to date is already at 10th Floor of Tower A. Fair weather continues to grace the month which maximized a good working pace for construction operations, especially for work shifting and material deliveries.
November 16 to December 15, 2009
October 16 to November 15, 2009
Concreting works already reached the 7th floor of Tower A, while bulk excavation works are in an advanced status at 97 percent. Civil works for the Sewage Treatment Plant has already been completed.
October 16 to November 15, 2009
Concreting works already reached the 5th floor of Tower A.
August 16 to September 15
Concreting works already reached the 3rd floor of Tower A.